Yemen LNG to Increase Production

Yemen LNG to Increase Production

Yemen LNG said it will complete the annual plant shutdown at Balhaf on 20th April, 9 days ahead of the original schedule.

The shutdown was advanced in response to a sabotage of the gas pipeline on 30th of March.

Six LNG cargoes had to be cancelled further to the sabotage. All May cargoes will be loaded on schedule, the company said in a statement.

We will increase LNG production to redeliver as much of the cancelled cargoes as possible before year end.” said Francois Rafin, the General Manager of Yemen LNG.

We are confident in the prompt reinforcement of the surveillance and protection of the pipeline; the mobilization of a new security deployment is already in progress.

LNG World News Staff, April 19, 2012; Image: Yemen LNG

Share this article

Follow LNG World News

Events>

<< Mar 2015 >>
MTWTFSS
23 24 25 26 27 28 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Flame Conference 2015

Known as the European meeting place for the global gas community, Flame is the annual meeting place for the industry where the most…

read more >

Fundamentals of LNG

Operational and commercial essentials of the Liquefied Natural Gas sector from IBC Academy…

read more >

LNG Congress Russia 2015

The main aim of the LNG Congress Russia 2015 is to create a strategic expert platform for successful discussion and search of solutions…

read more >

LNG Markets, Supply and Pricing

This course will provide you with a detailed knowledge when it comes to the workings of the LNG Value Chain and how the business fits together…

read more >