APLNG completes 90-day operational phase lenders’ test

APLNG completes 90-day operational phase lenders' test
Image courtesy of Origin

ConocoPhillips-operated Australia Pacific LNG concluded the 90-day operational phase of the two train project finance lenders’ test.

“All other elements of the project finance completion tests are on track and Australia Pacific LNG expects that formal certification that they have been satisfied will be provided during the first quarter of FY2018,” Origin Energy that holds a 37.5 percent stake in the project said on Friday.

When the formal certifications are received the remaining US$3.4 billion of shareholder guarantees relating to Australia Pacific LNG’s $8.5 billion project finance facility will be formally released.

Origin added that, during the 90-day period, Australia Pacific LNG achieved high operational performance across all key metrics associated with the test. The facility produced on average more than 10 per cent above nameplate capacity with high thermal efficiency and minimal downtime.

The $17 billion LNG project has a full production capacity of 9 million tons per year of the chilled fuel.

Shareholders in the Australia Pacific LNG project are ConocoPhillips (37.5%), Origin (37.5%) and Sinopec (25%).

Share this article

Follow LNG World News

Events>

<< Mar 2019 >>
MTWTFSS
25 26 27 28 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 31

LNG2019

LNG2019 is presented by the IGU, GTI and IIR, supported by the Shanghai Government and hosted by China LNG Association, China Gas Society, The Chinese Association of Refrigeration and China Gas Association.

read more >

CWC World Gas & Power Series – Brazil & the Americas Summit

Meet with the Gas, LNG & Power Industry in Brazil & the Americas

read more >

Downstream 2019

Renowned as the most significant global meeting place for Downstream professionals…

read more >