Australia: Santos GLNG Updates on Tunnel Boring Works

Only one kilometre remains before Santos GLNG’s tunnel boring machine (TBM) breaks through to the surface at Curtis Island, Gladstone.

The tunnel being constructed underneath The Narrows reached a distance of 3.3 kilometres this week and is now boring upwards having passed the tunnel’s deepest point.

Once the tunnel reaches its full length of 4.3 kilometres, pipe segments will be pulled into it and connected.

The tunnel will link the project’s gas fields at Fairview, north of Roma, to the liquefied natural gas plant on Curtis Island.

Work progresses at the reception pad to ready the area for the TBM’s arrival.

LNG World News Staff, November 08, 2013; Image: Santos

Share this article

Follow LNG World News

One thought on “Australia: Santos GLNG Updates on Tunnel Boring Works”

Comments are closed.

Events>

<< Jan 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2

Flame 2020

Flame is Europe’s largest and most influential meeting place for the global gas industry.

read more >

4th PNG Petroleum & Energy Summit

The CWC Group, in partnership with Kumul Petroleum Holdings Ltd.

read more >

FSRU World Congress 2020

FSRU World Congress 2020 will therefore focus on further Commercialising FSRUs through LNG-to-Power…

read more >

CWC World LNG & Gas Series: 12th Asia Pacific Summit

The 2020 Summit will offer an unrivaled programme covering relevant and significant discussion topics…

read more >