Bechtel sets last APLNG module in place

Bechtel sets last APLNG module in place

Bechtel said that it has completed the Australia Pacific LNG project’s heavy lift program with the setting of the final Train 2 module.

Module 202RA, which arrived on the job site late last year, was set in place following the completion of the final concrete foundations required to safely set the module.

Over the past two years, a total of 69 modules, weighing more than 43,000 tonnes, have been set in place on the APLNG job site, that’s equivalent to 78 fully loaded Qantas Airbus A380s, Bechtel said in a statement.

The successful placement of 202RA is a significant milestone for APLNG, with all 69 modules now in place and all big lifts on the job site complete. Most importantly, the heavy lift program was completed without any incidents or injuries.

Press Release; Image: Bechtel

Share this article

Follow LNG World News

Events>

<< Feb 2020 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 1

FSRU World Congress 2020

FSRU World Congress 2020 will therefore focus on further Commercialising FSRUs through LNG-to-Power…

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – Houston / Feb 2020

This three-day training program provides a unique opportunity to learn and apply the practical skills, knowledge and tools needed to:…

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – London / Mar 2020

This three-day training program provides a unique opportunity to learn and apply the practical skills…

read more >

3rd CWC Japan LNG & Gas Summit

As the only commercially focused forum for the Japanese LNG industry

read more >