Cheniere authorized to advance Sabine Pass Train 3 commissioning

Cheniere authorized to advance Sabine Pass Train 3 commissioning
Image courtesy of Cheniere

Cheniere’s Sabine Pass liquefaction project has been authorized to introduce feed gas and refrigerants into Train 3 and stage 2 OSBL facilities for commissioning. 

However, the US Federal Energy Regulatory Commission noted in its letter on Tuesday that this authorization does not grant introduction of natural gas or process fluids into areas not identified in the request.

In a recent report, Cheniere informed that the construction of Sabine Pass trains 3 and 4 is 91.8 percent complete and ahead of contractual schedule, with substantial completion expected in 2017.

Following the completion of maintenance and repair works at Sabine Pass that began in September, Cheniere restarted liquefaction activities at both Train 1 and Train 2.

 

LNG World News Staff

Share this article

Follow LNG World News

Events>

<< Sep 2019 >>
MTWTFSS
26 27 28 29 30 31 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 1 2 3 4 5 6

6th Mozambique Gas Summit & Exhibit

This year’s edition will have a revamped programme for attendees.

read more >

Offshore Energy Exhibition and Conference 2019

The three-day event includes an exhibition where an expected 600+ supply chain companies will showcase their products and services.

read more >

LNGgc London

LNGgc is a fantastic way of raising attendees’ company profile within this market and creating greater awareness of their brand…

read more >

5th CWC China LNG & Gas International Summit & Exhibition

5th CWC China LNG & Gas International Summit & Exhibition will return 16 – 17 October 2019, bringing together the key players…

read more >