Cheniere authorized to advance Sabine Pass Train 3 commissioning

Cheniere authorized to advance Sabine Pass Train 3 commissioning
Image courtesy of Cheniere

Cheniere’s Sabine Pass liquefaction project has been authorized to introduce feed gas and refrigerants into Train 3 and stage 2 OSBL facilities for commissioning. 

However, the US Federal Energy Regulatory Commission noted in its letter on Tuesday that this authorization does not grant introduction of natural gas or process fluids into areas not identified in the request.

In a recent report, Cheniere informed that the construction of Sabine Pass trains 3 and 4 is 91.8 percent complete and ahead of contractual schedule, with substantial completion expected in 2017.

Following the completion of maintenance and repair works at Sabine Pass that began in September, Cheniere restarted liquefaction activities at both Train 1 and Train 2.

 

LNG World News Staff

Share this article

Follow LNG World News

Events>

<< Jul 2019 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

LNGgc London

LNGgc is a fantastic way of raising attendees’ company profile within this market and creating greater awareness of their brand…

read more >

LNG Pricing, Trading & Hedging Singapore

LNG Pricing, Trading & Hedging training program has been completed by hundreds of leading traders, analysts, risk managers…

read more >

LNG Pricing, Trading & Hedging Houston

LNG Pricing, Trading & Hedging training program has been completed by hundreds of leading traders, analysts, risk managers…

read more >

World Gas Series: Morocco Summit

Bringing together key players in the gas value chain in Morocco, the World Gas Series:

read more >