Cheniere commissions Sabine Pass LNG’s Train 4

Cheniere commissions Sabine Pass LNG's Train 4
Sabine Pass Trains 1-4 (Image courtesy of Cheniere)

The US LNG export player, Cheniere, has reached substantial completion of the fourth liquefaction train at the Sabine Pass LNG project in Cameron Parish, Louisiana.

Commissioning has been completed and Cheniere’ EPC partner Bechtel has turned over care, custody, and control of Train 4 to the company, Cheniere’s statement reads.

Under a sale and purchase agreement with India’s GAIL, the date of first commercial delivery for Train 4 of the Sabine Pass liquefaction project is expected to occur in March 2018, upon which the SPA’s 20-year term commences.

With four trains online, the Sabine Pass plant will be able to produce up to 18 million tons per annum of the chilled fuel.

Cheniere is developing up to six trains at Sabine Pass.

The plant, currently the only such a facility to export US shale gas overseas, shipped more than 175 cargoes of LNG to 25 different countries in the period spanning from February 2016 to August 2017.

 

LNG World News Staff

Share this article

Follow LNG World News

Events>

<< Sep 2019 >>
MTWTFSS
26 27 28 29 30 31 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 1 2 3 4 5 6

6th Mozambique Gas Summit & Exhibit

This year’s edition will have a revamped programme for attendees.

read more >

Offshore Energy Exhibition and Conference 2019

The three-day event includes an exhibition where an expected 600+ supply chain companies will showcase their products and services.

read more >

LNGgc London

LNGgc is a fantastic way of raising attendees’ company profile within this market and creating greater awareness of their brand…

read more >

5th CWC China LNG & Gas International Summit & Exhibition

5th CWC China LNG & Gas International Summit & Exhibition will return 16 – 17 October 2019, bringing together the key players…

read more >