Cheniere’s Sabine Pass LNG export project moves ahead

Cheniere's Sabine Pass LNG export project moves ahead

Houston-based LNG player Cheniere filed construction activities report with FERC for its Sabine Pass LNG export terminal in Cameron Parish, Louisiana. 

The report covers activities of the Stage 1 (Trains 1 and 2) and Stage 2 (Trains 3 and 4) projects during the month of November.

According to the filing, Stage 1 Engineering and Procurement are 100% complete, Subcontract and direct hire Construction work are 52.8% and 53.4% complete, respectively. Stage 1 overall project completion is 79% against the plan of 80.2%.

Stage 2 Engineering is now 92.9% complete, Procurement is 72.6%, and Subcontract and direct hire Construction work are 31.2% and 13.6% complete, respectively. Overall project completion for Stage 2 is 49.8% against the plan of 50.0%.

Cheniere informed that construction is on track for the set completion targets for Train 1 and Train two as February 2016 and June 216 respectively. Trains 3 and 4 Substantial Completion Dates are April 2017 and August 2017.

LNG World News Staff; Image: Cheniere

Share this article

Follow LNG World News

Events>

<< Nov 2019 >>
MTWTFSS
28 29 30 31 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 1

2nd Global LNG Forum

Global LNG Forum is an exclusive networking and knowledge-sharing platform for top experts and business leaders in the industry.

read more >

Budapest LNG Summit 2019

The Budapest LNG Summit is a niche event focused on the up and coming LNG region of Central & Eastern Europe (CEE).

read more >

CWC World LNG Summit & Awards Evening

The CWC World LNG Summit & Awards Evening will be returning to Rome in 2019 to celebrate it’s 20th year.

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – Singapore / Jan 2019

This three-day training program provides a unique opportunity to learn and apply the practical skills, knowledge and tools needed to:…

read more >