Chevron: Gorgon LNG Project 78 Percent Complete

Chevron said on Tuesday that the company’s US$54 billion Gorgon LNG project in Australia is 78 percent complete, with 65 percent of the LNG already committed under long-term contracts.

Chevron also revealed that the start-up date for first LNG from the Gorgon project has been pushed back to mid-2015, instead of the first quarter, the company said in an investor update.

The company said that offshore pipe laying was now complete and that almost 6,000 people are working on constructing the massive LNG project.

Wheatstone LNG project, the company’s second LNG project in Australia, is 30 percent complete, with 85 percent of the project’s LNG committed under long-term contracts.

LNG World News Staff, March 12, 2014; Image: Chevron

 

 

 

 

 

Share this article

Follow LNG World News

Events>

<< Aug 2019 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31 1

LNGgc London

LNGgc is a fantastic way of raising attendees’ company profile within this market and creating greater awareness of their brand…

read more >

LNG Pricing, Trading & Hedging Singapore

LNG Pricing, Trading & Hedging training program has been completed by hundreds of leading traders, analysts, risk managers…

read more >

LNG Pricing, Trading & Hedging Houston

LNG Pricing, Trading & Hedging training program has been completed by hundreds of leading traders, analysts, risk managers…

read more >

World Gas Series: Morocco Summit

Bringing together key players in the gas value chain in Morocco, the World Gas Series:

read more >