CNOOC completes maintenance at Tianjin LNG terminal

CNOOC completes maintenance at Tianjin LNG terminal
Image courtesy of CNOOC

CNOOC Gas & Power has recently completed maintenance works at its Tianjin liquefied natural gas import terminal. 

The maintenance was completed during a four-day period before the gas flows to the national transmission network resumed on April 27, the company said in a statement.

Terminal operator said it has completed over 40 checks during the maintenance shutdown ‘improving the health of its equipment, following a busy winter period.

According to the company, a sub-station ball valve replacement has been completed, including various machinery, instruments and electrical components overhauls. Leak points at the high-pressure compressor were welded while work has also been carried out on the pipeline.

CNOOC noted that it was also the first time the maintenance at the Tianjin LNG has been completed independently.

Share this article

Follow LNG World News

Events>

<< Oct 2019 >>
MTWTFSS
30 1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31 1 2 3

Budapest LNG Summit 2019

The Budapest LNG Summit is a niche event focused on the up and coming LNG region of Central & Eastern Europe (CEE).

read more >

5th CWC China LNG & Gas International Summit & Exhibition

5th CWC China LNG & Gas International Summit & Exhibition will return 16 – 17 October 2019, bringing together the key players…

read more >

LNG Bunkering Mediterrean

The only 3-day course offering theoretical and practical training on LNG bunkering designed by the Mediterranean market leaders.   

read more >

6th Mozambique Gas Summit & Exhibit

This year’s edition will have a revamped programme for attendees.

read more >