DSME: Petronas first FLNG nearing completion

Daewoo Shipbuilding and Marine Engineering (DSME) said it has completed lifting and installation of all 21 topside modules for Petronas’ first floating LNG (FLNG) production unit.

The lifting of the first topside module for the PFLNG Satu began in September last year at the Quayside of DSME shipyard in Okpo, South Korea.

The modules, on which power generation and control functions instruments are installed, weigh about 2,000 tonnes each.

2

Petronas has appointed Technip and DSME as a consortium to jointly develop the FLNG facility with a capacity of 1.2 mtpa, 365-metre length, 60-metre width and 33-metre height.

Once the construction and installation phases complete in September 2015, PFLNG Satu will be moored in Kanowit field located 180 kilometres offshore Sarawak, Malaysia.

 

LNG World News Staff

Share this article

Follow LNG World News

Events>

<< Oct 2019 >>
MTWTFSS
30 1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31 1 2 3

CWC World LNG Summit & Awards Evening

The CWC World LNG Summit & Awards Evening will be returning to Rome in 2019 to celebrate it’s 20th year.

read more >

LNG Bunkering Mediterrean

The only 3-day course offering theoretical and practical training on LNG bunkering designed by the Mediterranean market leaders.   

read more >

6th Mozambique Gas Summit & Exhibit

This year’s edition will have a revamped programme for attendees.

read more >

FLNG World Congress 2019

2019 FLNG World Congress will bring together stakeholders across the floating liquefaction value…

read more >