Gallery: Cheniere’s Corpus Christi LNG project progresses

Gallery Cheniere's Corpus Christi LNG project progresses
Images courtesy of Cheniere

Cheniere’s Corpus Christi liquefaction project located on the U.S. Gulf Coast has reached 77.4 percent completion.

According to the Houston-based LNG player’s monthly report, the engineering has been completed with the procurement reaching 91 percent. Subcontract and direct hire construction work are at 51.1 percent and 52.1 percent respectively.

The site has generally been restored from the impacts of Hurricane Harvey, the October report reads.

Clean-up efforts are near completion and the major temporary warehouses have been repaired with most of the permanent plant equipment and bulk material have been inspected, with repairs and/or replacements underway.

During October the energization of the GIS and main substation was completed, the setting of Train 1 waste heat recovery units and GT stacks have started,  Train 1 mineral lube oil flushes and oil flashes for Methane and Ethylene Refrigeration Compressors also started during the month, as well as Derrick structure erection. Construction turned over 20 systems to startup through the end of October.

Cheniere has recently completed its FEED study on a midscale liquefaction solution for the Corpus Christi expansion project and began the process of amending the filing with the Federal Energy Regulatory Commission to incorporate midscale liquefaction technology.

The project involves up to seven midscale liquefaction trains adjacent to the Corpus Christi liquefaction project, each with an expected nominal production capacity of approximately 1.4 mtpa of LNG. The total expected nominal production capacity of the seven midscale trains is approximately 9.5 mtpa.

 

LNG World News Staff

Share this article

Follow LNG World News

Events>

<< Jun 2018 >>
MTWTFSS
28 29 30 31 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 1

Singapore International Bunkering Conference and Exhibition (SIBCON)

The 20th edition of the Singapore International Bunkering Conference and Exhibition (SIBCON) will be about inspiring change…

read more >

4th Annual Upstream West Africa Summit 2018

In June 2018, Senegal will play host to the No.1 Annual B2B Upstream Oil & Gas event, which will bring together the senior decision makers from across the prolific West Africa region to discuss the trends and challenges currently facing the Oil and Gas industry.

Since the discovery by Tullow Oil in 2007 of the Jubilee Field in Ghana, the Upstream sector has refocused its efforts to explore similar plays around the entire West and North West African coast. These efforts were rewarded with Cairn Energy’s prolific discovery in 2014 followed by Kosmos’ in 2015. The West Africa region has the industry’s spotlight firmly focused on further unlocking the potential of this largely underexplored region.

Companies that will be looking toward further unlocking the deepwater hydrocarbon potential of West Africa include: PETROSEN, BP, Kosmos Energy, Cairn Energy, FAR, Total E&P, Premier Oil, Shell, Tullow Oil along with the Ministries and key solution providers.

 More info

read more >

The 27th World Gas Conference (WGC 2018)

The 27th World Gas Conference (WGC 2018) will be the largest, most timely and most significant global gas conference and exhibition ever held.

read more >

Oil and Gas 2018

The conference will cover a wide range of topics and allow participants to discuss about the new technologies developed in Petroleum…

read more >