Last module for Santos GLNG completed

Last module for Santos GLNG completed

Santos GLNG said that the last LNG module has left Batangas in the Philippines and is now bound for Curtis Island.

The company also said that all 111 GLNG modules have been completed after two years of construction.

Earlier this month the company said that the US$18.5 billion Santos GLNG project is more than 85% complete and remains on track for first LNG in 2015.

 

LNG World News Staff, August 28, 2014; Image: Santos GLNG

Share this article

Follow LNG World News

2 thoughts on “Last module for Santos GLNG completed”

  1. Pingback: Eddie
  2. Pingback: Ricky

Comments are closed.

Events>

<< Apr 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

Flame 2020

Flame is Europe’s largest and most influential meeting place for the global gas industry.

read more >

4th PNG Petroleum & Energy Summit

The CWC Group, in partnership with Kumul Petroleum Holdings Ltd.

read more >

FSRU World Congress 2020

FSRU World Congress 2020 will therefore focus on further Commercialising FSRUs through LNG-to-Power…

read more >

CWC World LNG & Gas Series: 12th Asia Pacific Summit

The 2020 Summit will offer an unrivaled programme covering relevant and significant discussion topics…

read more >