Picture of the Day: GLNG Jetty

Santos said today that the GLNG jetty is over 95% complete with the installation of quick release mooring hooks and fenders complete, and installation of the gangway tower and pre-commissioning works commenced.

Overall, the GLNG project is 80% complete and remains on track for first LNG in 2015.

LNG World News Staff, April 17, 2014; Image: Santos

Share this article

Follow LNG World News

Events>

<< Feb 2020 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 1

2nd Central and Eastern European Small Scale LNG Forum

The Forum is for LNG industry leaders, who want to keep up to date with Small-Scale LNG latest trends and many other topics!

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – Houston / Feb 2020

This three-day training program provides a unique opportunity to learn and apply the practical skills, knowledge and tools needed to:…

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – London / Mar 2020

This three-day training program provides a unique opportunity to learn and apply the practical skills…

read more >

3rd CWC Japan LNG & Gas Summit

As the only commercially focused forum for the Japanese LNG industry

read more >