Sabine Pass liquefaction project moving forward

Sabine Pass liquefaction project moving forward

Sabine Pass LNG, a unit of Cheniere Energy, filed a report with the U.S. FERC covering construction activities through September at the Sabine Pass LNG export terminal in Cameron Parish, Louisiana.

Stage 1 (trains 1 and 2) engineering and procurement are each 99.9% complete and subcontract and direct hire construction work are 50.9% and 44.5% complete. Stage 1 overall project completion is 75.6% against the plan of 76.1%, according to the report.

Stage 2 (trains 3 and 4) engineering is now 88.3% complete, procurement is 63%, and subcontract and direct hire construction work are 26.8% and 8.5% complete. Overall project completion for Stage 2 is 42.8% against the plan of 42.6%.

Actual project progress continues to support the achievement of the scheduled substantial completion dates for Trains 1 and 2, which remain as February 2016 and June 2016, the report says.

Trains 3 and 4 substantial completion dates are April 2017 and August 2017.

LNG World News Staff; Image: Sabine Pass LNG

Share this article

Follow LNG World News

Events>

<< Sep 2019 >>
MTWTFSS
26 27 28 29 30 31 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 1 2 3 4 5 6

6th Mozambique Gas Summit & Exhibit

This year’s edition will have a revamped programme for attendees.

read more >

Offshore Energy Exhibition and Conference 2019

The three-day event includes an exhibition where an expected 600+ supply chain companies will showcase their products and services.

read more >

LNGgc London

LNGgc is a fantastic way of raising attendees’ company profile within this market and creating greater awareness of their brand…

read more >

5th CWC China LNG & Gas International Summit & Exhibition

5th CWC China LNG & Gas International Summit & Exhibition will return 16 – 17 October 2019, bringing together the key players…

read more >