Sabine Pass liquefaction project moving forward

Sabine Pass liquefaction project moving forward

Sabine Pass LNG, a unit of Cheniere Energy, filed a report with the U.S. FERC covering construction activities through September at the Sabine Pass LNG export terminal in Cameron Parish, Louisiana.

Stage 1 (trains 1 and 2) engineering and procurement are each 99.9% complete and subcontract and direct hire construction work are 50.9% and 44.5% complete. Stage 1 overall project completion is 75.6% against the plan of 76.1%, according to the report.

Stage 2 (trains 3 and 4) engineering is now 88.3% complete, procurement is 63%, and subcontract and direct hire construction work are 26.8% and 8.5% complete. Overall project completion for Stage 2 is 42.8% against the plan of 42.6%.

Actual project progress continues to support the achievement of the scheduled substantial completion dates for Trains 1 and 2, which remain as February 2016 and June 2016, the report says.

Trains 3 and 4 substantial completion dates are April 2017 and August 2017.

LNG World News Staff; Image: Sabine Pass LNG

Share this article

Follow LNG World News

Events>

<< Nov 2019 >>
MTWTFSS
28 29 30 31 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 1

LNG Pricing, Trading & Hedging: 3-Day Training Course – Singapore / Jan 2019

This three-day training program provides a unique opportunity to learn and apply the practical skills, knowledge and tools needed to:…

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – London / Nov 2019

This three-day training program provides a unique opportunity to learn and apply the practical skills, knowledge and tools needed to:…

read more >

FLNG World Congress 2019

2019 FLNG World Congress will bring together stakeholders across the floating liquefaction value…

read more >

Budapest LNG Summit 2019

The Budapest LNG Summit is a niche event focused on the up and coming LNG region of Central & Eastern Europe (CEE).

read more >