Sabine Pass liquefaction project moving forward

Sabine Pass liquefaction project moving forward

Sabine Pass LNG, a unit of Cheniere Energy, filed a report with the U.S. FERC covering construction activities through September at the Sabine Pass LNG export terminal in Cameron Parish, Louisiana.

Stage 1 (trains 1 and 2) engineering and procurement are each 99.9% complete and subcontract and direct hire construction work are 50.9% and 44.5% complete. Stage 1 overall project completion is 75.6% against the plan of 76.1%, according to the report.

Stage 2 (trains 3 and 4) engineering is now 88.3% complete, procurement is 63%, and subcontract and direct hire construction work are 26.8% and 8.5% complete. Overall project completion for Stage 2 is 42.8% against the plan of 42.6%.

Actual project progress continues to support the achievement of the scheduled substantial completion dates for Trains 1 and 2, which remain as February 2016 and June 2016, the report says.

Trains 3 and 4 substantial completion dates are April 2017 and August 2017.

LNG World News Staff; Image: Sabine Pass LNG

Share this article

Follow LNG World News

Events>

<< Jan 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2

Flame 2020

Flame is Europe’s largest and most influential meeting place for the global gas industry.

read more >

4th PNG Petroleum & Energy Summit

The CWC Group, in partnership with Kumul Petroleum Holdings Ltd.

read more >

FSRU World Congress 2020

FSRU World Congress 2020 will therefore focus on further Commercialising FSRUs through LNG-to-Power…

read more >

CWC World LNG & Gas Series: 12th Asia Pacific Summit

The 2020 Summit will offer an unrivaled programme covering relevant and significant discussion topics…

read more >