Sabine Pass LNG: Stage 1 Construction 63.3 Pct Complete

Sabine Pass LNG, a unit of Cheniere Energy, filed a report with the U.S. FERC covering construction activities through March at the Sabine Pass LNG terminal, located in Cameron Parish, Louisiana.

Stage 1 (trains 1 and 2) engineering is 96.0% complete, procurement is 94.6%, and subcontract and direct hire construction work are 37.7% and 21.0% complete, respectively. Stage 1 overall project completion is 63.3% against the plan of 65.1%.

Stage 2 (trains 3 and 4) engineering is now 55.3% complete, procurement is 44.6%, and subcontract and direct hire construction work are 14.0% and 0.6% complete, respectively. Overall project completion for Stage 2 is 27.1% against the plan of 24.5%.

Actual project progress continues to support the achievement of the scheduled substantial completion dates for trains 1 and 2, which remain as February 2016 and June 2016, respectively.

Trains 3 and 4 substantial completion dates are April 2017 and August 2017.

LNG World News Staff, April 23, 2014; Image: Sabine Pass LNG

Share this article

Follow LNG World News

Events>

<< Nov 2019 >>
MTWTFSS
28 29 30 31 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 1

CWC World LNG Summit & Awards Evening

The CWC World LNG Summit & Awards Evening will be returning to Rome in 2019 to celebrate it’s 20th year.

read more >

6th Mozambique Gas Summit & Exhibit

This year’s edition will have a revamped programme for attendees.

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – London / Nov 2019

This three-day training program provides a unique opportunity to learn and apply the practical skills, knowledge and tools needed to:…

read more >

FLNG World Congress 2019

2019 FLNG World Congress will bring together stakeholders across the floating liquefaction value…

read more >