Sabine Pass LNG: Stage 1 Construction 63.3 Pct Complete

Sabine Pass LNG, a unit of Cheniere Energy, filed a report with the U.S. FERC covering construction activities through March at the Sabine Pass LNG terminal, located in Cameron Parish, Louisiana.

Stage 1 (trains 1 and 2) engineering is 96.0% complete, procurement is 94.6%, and subcontract and direct hire construction work are 37.7% and 21.0% complete, respectively. Stage 1 overall project completion is 63.3% against the plan of 65.1%.

Stage 2 (trains 3 and 4) engineering is now 55.3% complete, procurement is 44.6%, and subcontract and direct hire construction work are 14.0% and 0.6% complete, respectively. Overall project completion for Stage 2 is 27.1% against the plan of 24.5%.

Actual project progress continues to support the achievement of the scheduled substantial completion dates for trains 1 and 2, which remain as February 2016 and June 2016, respectively.

Trains 3 and 4 substantial completion dates are April 2017 and August 2017.

LNG World News Staff, April 23, 2014; Image: Sabine Pass LNG

Share this article

Follow LNG World News

Events>

<< Sep 2019 >>
MTWTFSS
26 27 28 29 30 31 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 1 2 3 4 5 6

6th Mozambique Gas Summit & Exhibit

This year’s edition will have a revamped programme for attendees.

read more >

Offshore Energy Exhibition and Conference 2019

The three-day event includes an exhibition where an expected 600+ supply chain companies will showcase their products and services.

read more >

LNGgc London

LNGgc is a fantastic way of raising attendees’ company profile within this market and creating greater awareness of their brand…

read more >

5th CWC China LNG & Gas International Summit & Exhibition

5th CWC China LNG & Gas International Summit & Exhibition will return 16 – 17 October 2019, bringing together the key players…

read more >