Sabine Pass LNG: Stage 1 Construction 63.3 Pct Complete

Sabine Pass LNG, a unit of Cheniere Energy, filed a report with the U.S. FERC covering construction activities through March at the Sabine Pass LNG terminal, located in Cameron Parish, Louisiana.

Stage 1 (trains 1 and 2) engineering is 96.0% complete, procurement is 94.6%, and subcontract and direct hire construction work are 37.7% and 21.0% complete, respectively. Stage 1 overall project completion is 63.3% against the plan of 65.1%.

Stage 2 (trains 3 and 4) engineering is now 55.3% complete, procurement is 44.6%, and subcontract and direct hire construction work are 14.0% and 0.6% complete, respectively. Overall project completion for Stage 2 is 27.1% against the plan of 24.5%.

Actual project progress continues to support the achievement of the scheduled substantial completion dates for trains 1 and 2, which remain as February 2016 and June 2016, respectively.

Trains 3 and 4 substantial completion dates are April 2017 and August 2017.

LNG World News Staff, April 23, 2014; Image: Sabine Pass LNG

Share this article

Follow LNG World News

Events>

<< Dec 2019 >>
MTWTFSS
25 26 27 28 29 30 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

The 6th CWC China LNG & Gas International Exhibition & Summit

Following on from LNG 2019 and five successful editions in Beijing, the established China LNG & Gas International Exhibition & Summit…

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – Singapore / Jan 2019

This three-day training program provides a unique opportunity to learn and apply the practical skills, knowledge and tools needed to:…

read more >

American LNG Forum 2020

The American LNG Forum is your gateway to learning about the US LNG export industry,

read more >

2nd Global LNG Forum

Global LNG Forum is an exclusive networking and knowledge-sharing platform for top experts and business leaders in the industry.

read more >