Sabine Pass LNG: stage 1 construction 71.8 pct complete

Sabine Pass LNG: stage 1 construction 71.8 pct complete

Sabine Pass LNG, a unit of Cheniere Energy, filed a report with the U.S. FERC covering construction activities through July at the Sabine Pass LNG terminal, located in Cameron Parish, Louisiana.

Stage 1 (trains 1 and 2) engineering is 99.4% complete, procurement is 99.5%, and subcontract and direct hire construction work are 46.6% and 35.6% complete, respectively, for the period. Stage 1 overall project completion is 71.8% against the plan of 72.5%.

Stage 2 (trains 3 and 4) engineering is 81.3% complete, procurement is 58%, and subcontract and direct hire construction work are 24.7% and 5.1% complete, respectively. Overall project completion for stage 2 is 38.5% against the plan of 36.3%.

Actual project progress continues to support the achievement of the scheduled substantial completion dates for trains 1 and 2, which remain as February 2016 and June 2016, respectively.

Trains 3 and 4 substantial completion dates are April 2017 and August 2017.

 

LNG World News Staff, August 25, 2014; Image: Sabine Pass LNG

Share this article

Follow LNG World News

4 thoughts on “Sabine Pass LNG: stage 1 construction 71.8 pct complete”

  1. Pingback: clyde
  2. Pingback: ray
  3. Pingback: joseph

Comments are closed.

Events>

<< Apr 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

Flame 2020

Flame is Europe’s largest and most influential meeting place for the global gas industry.

read more >

4th PNG Petroleum & Energy Summit

The CWC Group, in partnership with Kumul Petroleum Holdings Ltd.

read more >

FSRU World Congress 2020

FSRU World Congress 2020 will therefore focus on further Commercialising FSRUs through LNG-to-Power…

read more >

CWC World LNG & Gas Series: 12th Asia Pacific Summit

The 2020 Summit will offer an unrivaled programme covering relevant and significant discussion topics…

read more >