Sabine Pass LNG updates expansion schedule

Sabine Pass LNG updates expansion schedule

Sabine Pass LNG, a unit of Cheniere, provided FERC with an updated construction schedule of the anticipated expansion of its LNG export terminal at Cameron Parish, Louisiana. 

The letter to the Federal Energy Regulatory Commission also enclosed updates on the pipeline expansion project.

The updated schedule is based on the substantial completion date guaranteed by Sabine Pass EPC contractor, stands in the letter, assuming a June 2015 completion of the regulatory process.

The company stated that a more expeditious permitting process might shorten the completion timeframe.

Under the updated schedule, stage 3 construction should begin in June 2015, with the pipeline construction start scheduled for June 2017. Pipeline is scheduled to be in service by December 2018 with Train 5 expected to be in service by December 2019. A possible train 6 would be in service when commercially feasible, stands in the letter.

LNG World News Staff; Image: Cheniere

Share this article

Follow LNG World News

Events>

<< Sep 2019 >>
MTWTFSS
26 27 28 29 30 31 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 1 2 3 4 5 6

6th Mozambique Gas Summit & Exhibit

This year’s edition will have a revamped programme for attendees.

read more >

Offshore Energy Exhibition and Conference 2019

The three-day event includes an exhibition where an expected 600+ supply chain companies will showcase their products and services.

read more >

LNGgc London

LNGgc is a fantastic way of raising attendees’ company profile within this market and creating greater awareness of their brand…

read more >

5th CWC China LNG & Gas International Summit & Exhibition

5th CWC China LNG & Gas International Summit & Exhibition will return 16 – 17 October 2019, bringing together the key players…

read more >