Santos GLNG 95 pct complete

GLNG 95 pct complete, first LNG in Q3

Santos of Australia said that its GLNG project on Curtis Island off Gladstone is approaching 95% completion and is expected to produce first LNG around the end of the third quarter this year.

Previous guidance for first LNG was in the second half of this year, the company said in a statement.

Santos Managing Director and Chief Executive Officer David Knox said the project has progressed well and is expected to be delivered on time and within the US$18.5 billion budget.

In a short video, Santos Vice President Downstream GLNG Rod Duke speaks about the progress and milestones the project achieved during the first quarter of 2015.

LNG World News Staff; Image: Santos GLNG

Share this article

Follow LNG World News

Events>

<< Feb 2020 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 1

Flame 2020

Flame is Europe’s largest and most influential meeting place for the global gas industry.

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – London / Mar 2020

This three-day training program provides a unique opportunity to learn and apply the practical skills…

read more >

3rd CWC Japan LNG & Gas Summit

As the only commercially focused forum for the Japanese LNG industry

read more >

Cryogenic Storage Tanks

The program committee looks forward to having the opportunity for intensive, objective and professional…

read more >