Santos GLNG Project 72 Pct Complete, Australia

LNG player Santos of Australia said in a project update on Wednesday that the company’s GLNG  project is 72 percent complete and on track for first LNG in 2015.

According to Santos, 224 wells have been drilled in the GLNG acreage year-to-date and the company is on track to drill over 230 wells in the GLNG acreage in 2013.

Santos GLNG

Over half of the Train 1 modules have been shipped from the module yard to Curtis Island, where the LNG plant is located. Eight of these modules are complete and ready for shipping, while 27 modules are under construction.

Santos also said that the PNG LNG project, where the company has a 13,5 percent stake is over 90% complete and on track for first LNG in 2H 2014.

LNG World News Staff, December 4, 2013; Image: Santos

 

 

 

 

 

Share this article

Follow LNG World News

One thought on “Santos GLNG Project 72 Pct Complete, Australia”

Comments are closed.

Events>

<< Jan 2018 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

Singapore Maritime Technology Conference and Exhibition (SMTC) 2018

The 3rd Singapore Maritime Technology Conference and Exhibition (SMTC) 2018…

read more >

CWC Japan LNG & Gas Summit

The inaugural CWC Japan LNG & Gas Summit, with participation and support from METI, JERA, Tokyo Gas and IEEJ, is the dedicated platform for international suppliers…

read more >

Asia Pacific Maritime and Offshore Exhibition 2018

7 years in the making, APM is the premier shipbuilding & marine, workboat and offshore exhibition in Asia…

read more >

CWC 2nd Papua New Guinea Petroleum & Energy Summit

The 2nd CWC Papua New Guinea Petroleum and Energy Summit is held under the patronage of the Prime Minister of Papua New Guinea…

read more >