Santos GLNG Project 72 Pct Complete, Australia

LNG player Santos of Australia said in a project update on Wednesday that the company’s GLNG  project is 72 percent complete and on track for first LNG in 2015.

According to Santos, 224 wells have been drilled in the GLNG acreage year-to-date and the company is on track to drill over 230 wells in the GLNG acreage in 2013.

Santos GLNG

Over half of the Train 1 modules have been shipped from the module yard to Curtis Island, where the LNG plant is located. Eight of these modules are complete and ready for shipping, while 27 modules are under construction.

Santos also said that the PNG LNG project, where the company has a 13,5 percent stake is over 90% complete and on track for first LNG in 2H 2014.

LNG World News Staff, December 4, 2013; Image: Santos

 

 

 

 

 

Share this article

Follow LNG World News

One thought on “Santos GLNG Project 72 Pct Complete, Australia”

Comments are closed.

Events>

<< Aug 2019 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31 1

LNGgc London

LNGgc is a fantastic way of raising attendees’ company profile within this market and creating greater awareness of their brand…

read more >

LNG Pricing, Trading & Hedging Singapore

LNG Pricing, Trading & Hedging training program has been completed by hundreds of leading traders, analysts, risk managers…

read more >

LNG Pricing, Trading & Hedging Houston

LNG Pricing, Trading & Hedging training program has been completed by hundreds of leading traders, analysts, risk managers…

read more >

World Gas Series: Morocco Summit

Bringing together key players in the gas value chain in Morocco, the World Gas Series:

read more >