Santos GLNG project over 80 pct complete

The US$18.5 billion Santos GLNG project is over 80% complete and on track for first LNG in 2015.

Santos of Australia, the operator of the LNG project on Curtis island, said in a presentation on its website that over 560 wells have been drilled as part of the GLNG project up to date. Santos expects to drill about 300 wells over 2014-15 and 200-300 wells per year over 2016-20.

The company is currently preparing for hydrostatic testing of the first GLNG tank which is planned for early July.

The GLNG jetty is over 95% complete with the installation of quick release mooring hooks, capstans, fenders, vessel access gangway tower and loading arms completed.

According to Santos, about 3,400 people are currently working on the GLNG plant and port.

LNG World News Staff, June 26, 2014; Image: Santos

 

 

 

Share this article

Follow LNG World News

2 thoughts on “Santos GLNG project over 80 pct complete”

  1. Pingback: Ian
  2. Pingback: Robert

Comments are closed.

Events>

<< Aug 2019 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31 1

5th CWC China LNG & Gas International Summit & Exhibition

5th CWC China LNG & Gas International Summit & Exhibition will return 16 – 17 October 2019, bringing together the key players…

read more >

LNG Pricing, Trading & Hedging Houston

LNG Pricing, Trading & Hedging training program has been completed by hundreds of leading traders, analysts, risk managers…

read more >

World Gas Series: Morocco Summit

Bringing together key players in the gas value chain in Morocco, the World Gas Series:

read more >

Offshore Energy Exhibition and Conference 2019

The three-day event includes an exhibition where an expected 600+ supply chain companies will showcase their products and services.

read more >