Santos GLNG project over 80 pct complete

The US$18.5 billion Santos GLNG project is over 80% complete and on track for first LNG in 2015.

Santos of Australia, the operator of the LNG project on Curtis island, said in a presentation on its website that over 560 wells have been drilled as part of the GLNG project up to date. Santos expects to drill about 300 wells over 2014-15 and 200-300 wells per year over 2016-20.

The company is currently preparing for hydrostatic testing of the first GLNG tank which is planned for early July.

The GLNG jetty is over 95% complete with the installation of quick release mooring hooks, capstans, fenders, vessel access gangway tower and loading arms completed.

According to Santos, about 3,400 people are currently working on the GLNG plant and port.

LNG World News Staff, June 26, 2014; Image: Santos

 

 

 

Share this article

Follow LNG World News

2 thoughts on “Santos GLNG project over 80 pct complete”

  1. Pingback: Ian
  2. Pingback: Robert

Comments are closed.

Events>

<< Dec 2019 >>
MTWTFSS
25 26 27 28 29 30 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

The 6th CWC China LNG & Gas International Exhibition & Summit

Following on from LNG 2019 and five successful editions in Beijing, the established China LNG & Gas International Exhibition & Summit…

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – Singapore / Jan 2019

This three-day training program provides a unique opportunity to learn and apply the practical skills, knowledge and tools needed to:…

read more >

American LNG Forum 2020

The American LNG Forum is your gateway to learning about the US LNG export industry,

read more >

2nd Global LNG Forum

Global LNG Forum is an exclusive networking and knowledge-sharing platform for top experts and business leaders in the industry.

read more >