Santos GLNG team reaches safety milestone

Santos GLNG team reaches safety milestone

Santos GLNG informed that its workforce reached a 1 million safe work hours on the LNG project located on Custis Island near Gladstone. 

At the start of the year, the company completed the loading jetty at the GLNG facility with all 111 LNG plant modules (82 train 1 and 29 train 2 modules) set on their foundations.

Commissioning of the LNG plant is well underway with the firing of the first gas turbine generator is expected in the coming weeks.

Pneumatic pressure testing of both LNG tanks is complete and installation of the perlite insulation is nearing completion on the first tank.

LNG World News Staff; Image: Santos GLNG

Share this article

Follow LNG World News

Events>

<< Dec 2019 >>
MTWTFSS
25 26 27 28 29 30 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

The 6th CWC China LNG & Gas International Exhibition & Summit

Following on from LNG 2019 and five successful editions in Beijing, the established China LNG & Gas International Exhibition & Summit…

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – Singapore / Jan 2019

This three-day training program provides a unique opportunity to learn and apply the practical skills, knowledge and tools needed to:…

read more >

American LNG Forum 2020

The American LNG Forum is your gateway to learning about the US LNG export industry,

read more >

2nd Global LNG Forum

Global LNG Forum is an exclusive networking and knowledge-sharing platform for top experts and business leaders in the industry.

read more >