Santos profit plunges 82 percent

Australia’s Santos, operator of the GLNG project, reported a half-year net profit of $37 million after tax, 82 per cent lower than the previous first half, reflecting significantly lower oil prices and a higher exploration expense.

The half-year results were also highlighted by improvements in production and significant cost reductions across the business, Santos said in its results report on Monday.

Strong operational performance – particularly from PNG LNG and Darwin LNG – saw Santos record production growth of 13 per cent compared to last year. However, the lower realised oil prices resulted in sales revenue declining by 15 per cent.

The average realised oil price was US$60 per barrel for the period, compared to US$115 in the previous first half – a 47 per cent reduction.

“Capital expenditure for the first half was 55% below 2014 levels and we cut the production costs per barrel by 11% to A$13.70 per barrel of oil equivalent,” Santos Managing Director and Chief Executive Officer David Knox  said.

Tightly managing costs will continue to be a key focus as we work through the current oil price environment,” Knox added.

The 2015 exploration program was weighted to the first half and resulted in exploration and evaluation expense of $194 million. The campaign of drilling in PNG and Malaysia produced the successful Bestari-1 oil discovery offshore Malaysia but did not result in other commercial finds.

Santos also reported that it had brought gas into its LNG Train 1 at the $US18.5 billion GLNG project on Curtis Island.

Other GLNG milestones achieved include bringing all major upstream processing facilities on line, completing commissioning of all LNG facility power generation and other utilities, unloading of the propane and ethylene refrigerant into storage and commissioning all six LNG Train 1 refrigeration compressors.

Over the coming weeks, the GLNG team will start up Train 1’s “front end” pre-treatment units before chilling down the “cold end” refrigeration units to make LNG.

Knox confirmed that the GLNG project remained on track to deliver first LNG around the end of the third quarter. “This project is progressing extremely well. GLNG’s upstream facilities are fully operational and we are in the final stages of commissioning on Curtis Island,” Knox added.

Santos said it retains a robust funding position with approximately $2.2 billion in cash and undrawn debt facilities available at the end of June.

 

LNG World News Staff; Image: Santos

 

Share this article

Follow LNG World News

Events>

<< Nov 2019 >>
MTWTFSS
28 29 30 31 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 1

2nd Global LNG Forum

Global LNG Forum is an exclusive networking and knowledge-sharing platform for top experts and business leaders in the industry.

read more >

Budapest LNG Summit 2019

The Budapest LNG Summit is a niche event focused on the up and coming LNG region of Central & Eastern Europe (CEE).

read more >

CWC World LNG Summit & Awards Evening

The CWC World LNG Summit & Awards Evening will be returning to Rome in 2019 to celebrate it’s 20th year.

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – Singapore / Jan 2019

This three-day training program provides a unique opportunity to learn and apply the practical skills, knowledge and tools needed to:…

read more >