Tennessee Gas Pipeline Starts Services at Two New Projects (USA)

Tennessee Gas Pipeline Company (TGP), a subsidiary of Kinder Morgan Energy Partners, L.P., placed the fully subscribed Northeast Upgrade Project (NEUP) in service on schedule Nov. 1.

The approximately $500 million project boosts capacity on TGP’s 300 Line system in Pennsylvania and New Jersey by 636,000 dekatherms per day (dth/d) and provides additional takeaway capacity from the Marcellus shale area.

TGP also placed into service its approximately $65 million Marcellus Pooling Point (MPP) project as scheduled on Nov. 1. The fully subscribed project provides about 240,000 dth/d of additional firm Marcellus transportation capacity on TGP’s pipeline system in Pennsylvania.

“We are delighted to place both the NEUP and MPP projects in service as scheduled and provide our customers with reliable, efficient pipeline service to move more Marcellus Shale natural gas to the growing northeast market,” said Natural Gas Pipelines East Region President Kimberly S. Watson. “We continue to make progress on approximately $300 million of additional TGP expansion projects that have been previously announced.”

LNG World News Staff, November 04, 2013; Image: Kinder Morgan

Share this article

Follow LNG World News

Events>

<< Feb 2020 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 1

Flame 2020

Flame is Europe’s largest and most influential meeting place for the global gas industry.

read more >

LNG Pricing, Trading & Hedging: 3-Day Training Course – London / Mar 2020

This three-day training program provides a unique opportunity to learn and apply the practical skills…

read more >

3rd CWC Japan LNG & Gas Summit

As the only commercially focused forum for the Japanese LNG industry

read more >

Cryogenic Storage Tanks

The program committee looks forward to having the opportunity for intensive, objective and professional…

read more >