USA: Sabine Pass construction slightly behind schedule

Houston-based Cheniere said that overall construction on its Sabine pass liquefaction and export project is slightly behind schedule.

Overall, Train 1 and 2 project progress is 96.1% complete against a plan of 98.2%. Train 3 and 4 project progress is 76.7% complete against a plan of 81.8%,” Cheniere said in the October report filed with the U.S. FERC.

However, Cheniere said that the current project progress supports the planned completion for Trains 1 and 2 by March and June in 2016, respectively. Trains 3 and 4 targeted substantial completion dates are April and August 2017.

Cheniere is building liquefaction and export facilities at its existing import terminal located along the Sabine Pass River on the border between Texas and Louisiana.

The Sabine Pass facility is expected to start receiving feed gas by the end of the year with the first cargo to be shipped in January 2016.

 

LNG World News Staff; Image: Cheniere

Share this article

Follow LNG World News

Events>

<< Sep 2019 >>
MTWTFSS
26 27 28 29 30 31 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 1 2 3 4 5 6

6th Mozambique Gas Summit & Exhibit

This year’s edition will have a revamped programme for attendees.

read more >

Offshore Energy Exhibition and Conference 2019

The three-day event includes an exhibition where an expected 600+ supply chain companies will showcase their products and services.

read more >

LNGgc London

LNGgc is a fantastic way of raising attendees’ company profile within this market and creating greater awareness of their brand…

read more >

5th CWC China LNG & Gas International Summit & Exhibition

5th CWC China LNG & Gas International Summit & Exhibition will return 16 – 17 October 2019, bringing together the key players…

read more >