Yemen LNG to Increase Production

Yemen LNG to Increase Production

Yemen LNG said it will complete the annual plant shutdown at Balhaf on 20th April, 9 days ahead of the original schedule.

The shutdown was advanced in response to a sabotage of the gas pipeline on 30th of March.

Six LNG cargoes had to be cancelled further to the sabotage. All May cargoes will be loaded on schedule, the company said in a statement.

We will increase LNG production to redeliver as much of the cancelled cargoes as possible before year end.” said Francois Rafin, the General Manager of Yemen LNG.

We are confident in the prompt reinforcement of the surveillance and protection of the pipeline; the mobilization of a new security deployment is already in progress.

LNG World News Staff, April 19, 2012; Image: Yemen LNG

Share this article

Follow LNG World News

Events>

<< Jan 2018 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

Singapore Maritime Technology Conference and Exhibition (SMTC) 2018

The 3rd Singapore Maritime Technology Conference and Exhibition (SMTC) 2018…

read more >

CWC Japan LNG & Gas Summit

The inaugural CWC Japan LNG & Gas Summit, with participation and support from METI, JERA, Tokyo Gas and IEEJ, is the dedicated platform for international suppliers…

read more >

Asia Pacific Maritime and Offshore Exhibition 2018

7 years in the making, APM is the premier shipbuilding & marine, workboat and offshore exhibition in Asia…

read more >

CWC 2nd Papua New Guinea Petroleum & Energy Summit

The 2nd CWC Papua New Guinea Petroleum and Energy Summit is held under the patronage of the Prime Minister of Papua New Guinea…

read more >